Please note the map above is only a representation and not an exact location of our construction route.
Project Phase:

Progress Updates:
August 7, 2025:
The Evansville North fiber project is complete! All homes or businesses have been installed with fiber-optic service.
February 6, 2025:
We have completed some of the splicing for the Evansville North Fiber Project. We are reaching out to the customers who are ready to schedule their fiber optic cutover. If you haven’t heard from our team, please call / text us at (320) 834-7253 to schedule your fiber optic installation!
October 2, 2024:
We have completed the mainline and fiber drops for the Evansville fiber project. The next step will be splicing.
August 9, 2024:
We are currently constructing the mainline and fiber drops for the Evansville North Fiber Project! If you are in this project area, please give us a call at (320) 834-7253 as soon as possible to schedule your site visit!

May 16, 2024:
We are busy scheduling site visits for the Evansville North Fiber Project! If you are in this project area, please give us a call at (320) 834-7253 as soon as possible to schedule your site visit!
April 4, 2024:
The Evansville North Project is in the hopper for 2024 construction! We will be passing 119 co-op members’ homes or businesses in the town of Evansville with fiber-optic cable. We’re doing our best to get fiber-optics delivered to your neighborhood as quickly as possible. While you wait, we get busy! We’re planning construction areas, working with local authorities for permits, engineering your network and lots of other behind the scenes work. Learn about what to expect here.
This includes some locations along:
- 1st Ave
- Alexandria St
- County Road 82 NW
- Douglas St
- Highland St
- Johnson St
- Kron St
- Main St
- Main St NW
- Meeker Ct
- Meeker St
- Minnesota St
- N Gran St
- Railroad St
- St Paul St