Please note the map above is only a representation and not an exact location of our construction route.
Progress Updates:
April 25, 2026:
The Utopia project is complete! All homes or businesses have been installed with fiber-optic service.
April 2, 2026:
Splicing is complete and we are ready to start installs! Call/text us at (320) 834-7253 to schedule.
March 26, 2026:
We have started splicing the Utopia Fiber Project.
November 13, 2025:
The main line and fiber drops are complete for the Utopia Fiber Project. The next step will be splicing.
November 5, 2025:
Locates have been called in for the Utopia Fiber Project. Once all of the underground facilities have been marked, construction will begin! If you haven’t scheduled your fiber optic site visit yet, please give us a call at (320) 834-7253 as soon as possible!
March 5, 2025:
The Utopia Project is in the hopper for 2025 construction! We will be passing 9 co-op members’ homes or businesses with fiber-optic cable. We’re doing our best to get fiber-optics delivered to your neighborhood as quickly as possible. While you wait, we get busy! We’re planning construction areas, working with local authorities for permits, engineering your network and lots of other behind the scenes work. Learn about what to expect here.
We have started scheduling site visits for the project so we will be ready to start construction in the summer. If you haven’t scheduled your fiber optic site visit yet, please give us a call at (320) 834-7253 as soon as possible!
This includes some locations along:
- Co Rd 58 NW
- Utopia Dr NW