Please note the map above is only a representation and not an exact location of our construction route.
Project Phase:

Progress Updates:
May 18, 2026:
Construction of fiber drops to each home or business is half way done in the Mary Lane Project!

May 12, 2026:
Mainline construction is complete and we will begin fiber drops soon! If you haven’t scheduled your fiber-optic site visit yet, please give us a call at (320) 834-7253 as soon as possible!
April 23, 2026:
Fiber mainline construction has officially kicked off in the Mary Lane Project. If you haven’t scheduled your fiber-optic site visit yet, please give us a call at (320) 834-7253 as soon as possible!
April 1, 2026:
The Mary Lane Fiber Project is in the hopper for 2026 construction! We will be passing 54 co-op members’ homes or businesses with fiber-optic cable. We’re doing our best to get fiber-optics delivered to your neighborhood as quickly as possible. While you wait, we get busy! We’re planning construction areas, working with local authorities for permits, engineering your network and lots of other behind the scenes work. Learn about what to expect here.
We’ve started scheduling site visits for the project so we will be ready to start construction this summer. If you haven’t scheduled your fiber-optic site visit yet, please give us a call at (320) 834-7253 as soon as possible!
This includes some locations along:
- Mary Ln NW
- West Shore Dr NW