Please note the map above is only a representation and not an exact location of our construction route.
October 19, 2020 Update:
Construction is 75% complete. We are scheduling installs for the areas where construction and splicing are finished. Our team will be reaching out to you soon, if they haven’t already, to schedule your install. The remainder of this project will be constructed in 2021. If you have any questions, please fill out our form here.
June 23, 2020 Update:
Work on our West Lake Ida project has begun! This is our biggest project of the summer with 325 locations being targeted for fiber-optic connectivity.
March 23, 2020 Update:
Construction begins summer of 2020! We’re passing 325 co-op members’ homes or businesses in the West Lake Ida area with fiber-optic cable. This includes some locations along:
- Breezy Circle NW
- Christopherson Road NW
- Circle Drive NW
- County Road 6 NW
- County Road 22 NW
- Ida View Court
- Ida View Drive NW
- Kaycee Lane NW
- Lake Ida Way NW
- Mallard Lane NW
- Memory Lane NW
- Oakridge Road NW
- Oakridge Lane NW
- Omaha Lane NW
- Pleasant Grove NW
- Shady Haven Drive NW
- Tasha Drive NW
- Wahtomin Trail NW
- Water Lily Trail NW
If you’re one of those people, we’ll be getting in touch with you soon, if not already. Before we can begin construction, we first need to plan out and place flags where the cable will be constructed to your home.
Here’s what we need from you:
- Call (320) 834-7253 or email us at myfiber@gardonville.net to schedule a site visit.
- Let us know what date and time works for you.
- Let us know what’s the best way to contact you.
- That’s it! We’ll do the rest.