Please note the map above is only a representation and not an exact location of our construction route.
Project Phase:

Progress Updates:
June 24, 2024:
The Schuelke Beach fiber project is complete! All homes or businesses have been installed with fiber-optic service.
November 6, 2023:
We have completed the splicing for the Schuelke Beach fiber project. We are scheduling installations for this project. Call / text us at (320) 834-7253 to schedule your fiber optic installation!
August 23, 2023:
We are splicing the Schuelke Beach fiber project.
August 10, 2023:
We have completed the mainline and fiber drops for the Schuelke Beach fiber project. The next step is splicing.
July 21, 2023:
We have started constructing the mainline and fiber drops for the Schuelke Beach fiber project. If you have not scheduled your site visit yet, please call/text (320) 834-7253 or click the button above ASAP.
March 21, 2023:
There may still be snow on the ground, but we are in the full swing of scheduling site visits! If you are in this project area, please give us a call at (320) 834-7253 or toll free 1-888-219-4145 as soon as possible.
March 3, 2023:
The Schuelke Beach Road Project is in the hopper for 2023 construction! We will be passing 78 co-op members’ homes or businesses in the Schuelke Beach Road area with fiber-optic cable. We’re doing our best to get fiber-optics delivered to your neighborhood as quickly as possible. While you wait, we get busy! We’re planning construction areas, working with local authorities for permits, engineering your network and lots of other behind the scenes work. Learn about what to expect here.
This includes some locations along:
- Basswood Shores Ln NW
- Diedrich Shores Rd NW
- Ellis Lake Rd NW
- Miltona West Rd NW
- Schuelke Beach Rd NW
- Schuelke Ln NW
- Spring Lake Rd NW