Please note the map above is only a representation and not an exact location of our construction route.
May 16, 2022 Update:
The mainline and fiber drop construction is complete for phase 1. Splicing will begin this week!
April 25, 2022 Update:
The first phase of the Lees Circle project is underway. Mainline construction will be starting soon! If you have not scheduled your site visit yet, please call / text (320) 834-7253 as soon as possible!
March 29, 2022 Update:
The Lees Circle Project is in the hopper for 2022 construction! We will be passing 69 co-op members’ homes or businesses in the Lees Circle area with fiber-optic cable. We’re doing our best to get fiber-optics delivered to your neighborhood as quickly as possible. While you wait, we get busy! We’re planning construction areas, working with local authorities for permits, engineering your network and lots of other behind the scenes work. Learn about what to expect here.
This includes some locations along:
- Centennial Dr NW
- Co Rd 82 NW
- 39th Ave NW
- Pleasant Grove NW
- 70th St NW
- 51st St NW
- Lees Circle NW