Please note the map above is only a representation and not an exact location of our construction route.
October 19, 2020 Update:
Construction and splicing are complete! Please call our office at (320) 834-7253 to chat with customer care about what services fit your needs.
June 10, 2020 Update:
Our crew is working on the Krohnfeldt Drive project today. 24 homes will be getting fiber-optic drops this week!
March 25, 2020 Update:
Gardonville has been awarded a Minnesota Border to Border Development Grant for the Krohnfeldt Drive neighborhood! Our goal is to have fiber-optic cable plowed by fall of 2020, with services available to 24 residents around January 2021.