Please note the map above is only a representation and not an exact location of our construction route.
Project Phase:

Progress Updates:
December 17, 2024:
The County Road 8 East fiber project is complete! All homes or businesses have been installed with fiber-optic service.
September 6, 2024:
We are currently scheduling installations for the County Road 8 East Fiber Project! If you have received a notification from us, please call or text us at (320) 834-7253 to schedule your fiber-optic cutover as soon as possible!
August 20, 2024:
We have finished constructing the mainline and fiber drops for the County Road 8 East Fiber Project! The next step will be splicing.
August 14, 2024:
We are currently constructing the mainline and fiber drops for the County Road 8 East Fiber Project!
May 16, 2024:
We are busy scheduling site visits for the County Road 8 East Fiber Project! If you are in this project area, please give us a call at (320) 834-7253 as soon as possible to schedule your site visit!
April 4, 2024:
The County Road 8 East Project is in the hopper for 2024 construction! We will be passing 18 co-op members’ homes or businesses in the County Road 8 East area with fiber-optic cable. We’re doing our best to get fiber-optics delivered to your neighborhood as quickly as possible. While you wait, we get busy! We’re planning construction areas, working with local authorities for permits, engineering your network and lots of other behind the scenes work. Learn about what to expect here.
This includes some locations along:
- Co Rd 8 NW