Please note the map above is only a representation and not an exact location of our construction route.
County Road 34 Phase 2 – 2022:

September 12, 2023 Update:
This fiber project is complete! All homes or businesses have been installed with fiber-optic service.
December 7, 2022 Update:
If you have not scheduled your fiber optic install yet, please call or text us at (320) 834-7253 to schedule your fiber-optic cutover as soon as possible!
October 26, 2022 Update:
As homes get spliced and pass all testing, we’ll reach out to you to schedule your fiber optic install. Watch for postcards, calls and text messages from us. Once you hear from us, please text 320-834-7253 or call toll free 1-888-219-4145 as soon as possible to schedule your install!
September 23, 2022 Update:
We’re actively working on multiple phases of construction: fiber drops, splicing and installation. As homes get spliced and pass all testing, we’ll reach out to you to schedule your fiber optic install. Watch for postcards, calls and text messages from us. Once you hear from us, please text 320-834-7253 or call toll free 1-888-219-4145 as soon as possible to schedule your install!
July 12, 2022 Update:
We’re currently working on the mainline and fiber drops. We have been sending out postcards, but are still waiting to hear back from a few homes. If you have not scheduled your site visit yet, please call / text (320) 834-7253 as soon as possible! You can also call toll free: 1-888-219-4145.
May 27, 2022 Update:
We have been trying to reach the remaining homes in this project to schedule the site visits before we start up construction this summer. If you have not scheduled your site visit yet, please call / text (320) 834-7253 as soon as possible! You can also call toll free: 1-888-219-4145.
April 25, 2022 Update:
We are anxiously awaiting spring and warmer weather here in Minnesota so we can start up our construction season! There are still quite a few homes that we haven’t heard from in this project. We have been sending out marketing materials and going door to door to the homes and businesses to schedule site visits for this project. If you have not scheduled your site visit yet, please call / text (320) 834-7253 as soon as possible! You can also call toll free: 1-888-219-4145.
March 23, 2022 Update:
We have been sending out marketing materials to the homes and businesses to schedule site visits for this project. If you have not scheduled your site visit yet, please call / text (320) 834-7253 as soon as possible!
December 30, 2021 Update:
We will be breaking ground on phase 2 in the spring of 2022. To be as efficient as possible, we have started scheduling site visits. If you are in this project area, we will be sending postcards to notify you. If you received a postcard, please give us a call at (320) 834-7253 as soon as possible.
County Road 34 Phase 1 – 2021:

February 2, 2022 Update:
All homes in phase 1 have been spliced and passed testing. If you haven’t scheduled your fiber-optic installation yet, please give us a call at (320) 834-7253.
December 30, 2021 Update:
There are a few homes left to splice in phase 1. We are scheduling installations as soon as we can. If you have received a notification from our team that your home is ready to install, please give us a call at (320) 834-7253 as soon as possible.
November 30, 2021 Update:
We are still working on splicing for this project. We are scheduling installations as soon as everything passes testing!
November 2, 2021 Update:
The majority of this project is in the splicing phase. As locations get spliced and pass testing, we are getting them scheduled for installation.
October 5, 2021 Update:
We are still working on the mainline and fiber drops. If you have not scheduled your site visit, please call us at (320) 834-7253 as soon as possible.
August 17, 2021 Update:
We’re currently working on the mainline and fiber drops. We have been sending out postcards, but are still waiting to hear back from quite a few homes. If you have not scheduled your site visit, please call us at (320) 834-7253 as soon as possible.
July 22, 2021 Update:
We are very excited that we have started the mainline construction. We have been sending out postcards, but are still waiting to hear back from quite a few homes. If you have not scheduled your site visit, please call us at (320) 834-7253 as soon as possible.
May 26, 2021 Update:
We’re working on scheduling site visits. If you have not scheduled your site visit, please call us at (320) 834-7253 as soon as possible.
February 2, 2021 Update:
Gardonville has been awarded a Border-to-Border Broadband Grant with the Minnesota DEED Office of Broadband Development in the County Road 34 neighborhood! 615 homes and businesses that are currently unserved with adequate internet will get fiber-optic connectivity. If you think you might live in this area, show us your interest in getting service by filling out our form here.