Project Phase:
Progress Updates:
August 23, 2022:
This fiber project is complete! All homes or businesses have been installed with fiber-optic service.
August 2, 2022:
We have completed the splicing for this project and are ready for installations! Please call or text us at (320) 834-7253 to schedule your fiber-optic cutover as soon as possible!
June 15, 2022:
The mainline and fiber drops are complete! The next step is splicing.
June 8, 2022:
We are moving ahead with the 285th Street Project! We will start construction on the mainline and individual fiber drops for this project soon. Before we start digging, we call in a locate.
February 16, 2021:
All of the site visits for this project have been completed. We will begin construction during the summer of 2022.
June 29, 2021:
We are very excited to be moving ahead with our 285th Street project! Before we can start digging, we first need to schedule a site visit. A Gardonville technician will meet with you to discuss how the fiber-optics will be brought up to your home. They will mount a nid on the exterior of your house, and you’ll discuss any privately owned underground facilities (pet fences, sprinkler systems, well, septic systems, electricity, etc).
If you haven’t scheduled your site visit, but we’ve been trying to reach you, please call us at (320) 834-7253.
June 2, 2021:
The 285th Street Project is in the hopper for 2021-2022 construction! We’re passing 2 co-op members’ homes or businesses with fiber-optic cable. We’re doing our best to get fiber-optics delivered to your neighborhood as quickly as possible. While you wait, we get busy! We’re planning construction areas, working with local authorities for permits, engineering your network and lots of other behind the scenes work.