Progress Updates:
April 2, 2026:
The North Lake Ida project is complete! All homes or businesses have been installed with fiber-optic service.
November 4, 2025:
We are working on splicing the North Lake Ida fiber project.
October 17, 2025:
We have completed the mainline and fiber drops for the North Lake Ida fiber project. The next step will be splicing.
September 25, 2025:
We have resumed construction on the mainline and fiber drops for the North Lake Ida fiber project. If you haven’t scheduled your site visit yet, please give us a call at (320) 834-7253 or toll free 1-888-219-4145 as soon as possible.
![]() |
August 12, 2025:
We have started construction on the mainline for the North Lake Ida fiber project. If you haven’t scheduled your site visit yet, please give us a call at (320) 834-7253 or toll free 1-888-219-4145 as soon as possible.
![]() |
August 7, 2025:
The North Lake Ida Project is in the hopper for 2025 construction! We will be passing 62 co-op members’ homes or businesses in the North Lake Ida area with fiber-optic cable. We’re doing our best to get fiber-optics delivered to your neighborhood as quickly as possible. While you wait, we get busy! We’re planning construction areas, working with local authorities for permits, engineering your network and lots of other behind the scenes work. Learn about what to expect here.
This includes some locations along:
- Little Ida Beach Rd NW