Please note the map above is only a representation and not an exact location of our construction route.
Project Phase:

Progress Updates:
March 26, 2026:
Splicing is complete for the Garfield South Fiber Project. We are scheduling installations for this project. Call / text us at (320) 834-7253 to schedule your fiber optic installation!
September 25, 2025:
We are working on splicing the Garfield South Fiber Project.
September 15, 2025:
Construction is almost complete for Garfield South Fiber Project! Once construction is complete, we will start splicing.
August 20, 2025:
Construction has started for the Garfield South Fiber Project! If you haven’t scheduled your fiber optic site visit yet, please give us a call at (320) 834-7253 as soon as possible!
March 6, 2025:
The Garfield South Project is in the hopper for 2025 construction! We will be passing 52 co-op members’ homes or businesses with fiber-optic cable in the town of Garfield. We’re doing our best to get fiber-optics delivered to your neighborhood as quickly as possible. While you wait, we get busy! We’re planning construction areas, working with local authorities for permits, engineering your network and lots of other behind the scenes work. Learn about what to expect here.
We have started scheduling site visits for the project so we will be ready to start construction in the summer. If you haven’t scheduled your fiber optic site visit yet, please give us a call at (320) 834-7253 as soon as possible!
This includes some locations along:
- 39th Ave NW
- Co Rd 40 NW
- Co Rd 82 NW
- Douglas St
- Hunter Ln
- Linser St
- Sanstead St W