Project Phase:

Progress Updates:
December 17, 2024:
The Little Ida Beach fiber project is complete! All homes or businesses have been installed with fiber-optic service.
August 20, 2024:
We have completed splicing the Little Ida Beach project and have started scheduling installations! If you have received a notification from us, please call or text us at (320) 834-7253 to schedule your fiber-optic cutover as soon as possible!
July 23, 2024:
We have started splicing the Little Ida Beach fiber project.
July 10, 2024:
We have completed the mainline and fiber drops for the Little Ida Beach fiber project. The next step will be splicing.
July 2, 2024:
We are currently constructing the mainline and fiber drops for the Little Ida Beach fiber project!
June 24, 2024:
Site visits are complete and we will be starting construction soon! We will be calling in locates so you will see flags in the Little Ida Beach project area prior to us breaking ground.
April 4, 2024:
The Little Ida Beach Project is in the hopper for 2024 construction! We will be passing 22 co-op members’ homes or businesses in the Little Ida Beach area with fiber-optic cable. We’re doing our best to get fiber-optics delivered to your neighborhood as quickly as possible. While you wait, we get busy! We’re planning construction areas, working with local authorities for permits, engineering your network and lots of other behind the scenes work. Learn about what to expect here.
This includes some locations along:
- Little Ida Beach Rd NW